The fact that the PWG’s evaluation was heavily favouring Walkley was due to several reasons.  It was evident to me, from the outset,  that Walkley would win because of the makeup of the group – resident community associations, environmental and naturalist organizations making up 80% of the group. 

The fact that the public opinion favours Walkley should be no surprise – we want it put to proper use, and reserve green uses for Ottawa’s limited greenspace. 

Even the EA describes the “ideal site” as having the following characteristics, characteristcs that largely describe Walkley Yard: 

• Close proximity/access to N-S line; 

• Conveniently accessible by trains from the E-W line for heavy repairs; 

• Existing rail yard (benefits of having the required infrastructure and minimizing the number of new contaminants potentially added to the system); 

• Away from core natural areas and sensitive ecosystems; 

• Away from watercourses ; 

• Away from areas with high groundwater tables or recharge/discharge areas; 

Walkley is the only choice for a train yard.  This choice was backed up by all community members, including the those who live in the Walkley area, and James Allen from the Ottawa Central Railway.   

At the end of the PWG process, there wasn't a single objection to the recommendation we came to.

Costs

 

The technical team actually favours the cost category highly as evident in their weighted scoring on page 61 of the report.  Their high importance on cost is no surprise – they know council will also put high importance on saving costs.  But, is this the right focus for city planning?  If council always chose the cheapest option we’d be in terrible shape – and we wouldn’t even have the current O-Train. 

The cost figures presented at the PWG were contested by members of the group – not only because we weren’t allowed to see the cost breakdown of the figures but because the costs for Walkley seemed high.  This was confirmed from external review. 

We were told the capital costs of each site were comprised of:

 

We know CPRail is asking $5M for Walkley which leaves 2.5 to 4 Million to the other components (according to the costs in the report).  I feel this difference is exaggerated and I hope that those who do see the cost breakdown scrutinize these components. 

The Bowesville site also requires a connecting track of a similar length and therefore the incremental capital cost, for that component, would be about the same for both sites.   

But, in terms of cost savings, we see that the Mayor and staff are fully capable of finding ways to save money in some areas of the LRT project  to fund other parts of it.  I applaud this effort, and suggest that the same can be done to make up the difference in cost, between Walkley and Bowesville.

The MOU

 

The MOU between the federal, provincial signatories and the city provides both a financial reassurance and confirmation of project scope described in Schedule A.   

It’s interesting to note that the Walkley yard is the preferred site in the MOU, and I suspect it a deciding factor on securing the much-needed funding from the senior governments, since they place high importance on brownfield reuse and preservation of greenspace. 

To change the desired site from Walkley to Bowesville will require consideration and approval from these governments for the upcoming “formal agreement” to go forward. 

In Summary

 

In summary, I urge council not to place too high an importance on cost; consider brownfield reuse incentives that are available (and not factored in to the costs), and keep in mind that the best location for a maintenance and storage facility is at the center of both N-S and E-W lines. 

Finally, if I may quote your speech on Earth Day, Mr. Mayor, you said that the Environment is “the highest priority of this council”.  I sincerely hope that this is evidenced by a council vote to preserve greenspace and reuse the Walkley Yard. 

Thank You

Ron Rancourt,  N-S PWG member, site evaluation for maintenance yard facility

 

5-minute speech to Transportation and Economic Development Committee

May 16, 2006

ronrancourt@gmail.com

613-521-1272